What’s the Operation Steps for Transformer Start-Up?
What’s the Operation Steps for Transformer Start-Up? (1) For transformers using forced oil circulation, the cooling system should be activated before commissioning. In the case of forced oil circulation water-cooled transformers, the oil system must be activated first, followed by the water system. After discontinuing the water cooling system in winter, the water should be completely drained. (2) If circuit breakers are present, they must be used for commissioning. In the absence of circuit breakers, isolating switches within the specified capacity range can be used for commissioning. (3) The energization of the transformer should be carried out from the power supply side equipped with protective devices. (4) In systems with a […]